Abu Talat Wastewater Station - Egypt

Water & Wastewater   ::  Ongoing Projects   ::  2024  ::  

The project includes:
·  A treatment plant with a capacity of 35 thousand m3/day,
·  Force main crossings, 2 direct pipes under the West Nubariya drain
·  a double direct pipe under Alexandria-Matrouh Road, and force mains (1200 mm, 800 mm, and 500 mm diameter) starting from the main lift station and the sub-lift station in the windward until the treatment plant in the leeward.
·  The latest advanced and specialized methods were used in implementing tunnels whose depths reach more than 13 meters below the surface of the earth, in addition to the drying work and reducing the water level to a depth of 8 meters below the surface of the earth.