Marriotia Axis - Egypt
Bridges & Flyovers
:: Completed Projects
:: 2009 ::
Construction of an axis, with a total length 2km. It is starting from the axis's inlets and outlets connected with the Eastern Arc of the Ring Road.
The starting date: 13th August, 2007.
The completion date: 1st November, 2009.
The execution period: 30 months.
The client: Greater Cairo Urban Authority.
The project total value: EGP 430 million.