Bokoro - Arbtchatk Road - Chad
                    
                    
                        Roads
                          ::  Completed Projects
                          ::  2011  ::  
                    
                    
                    
                    
                        
                            Project Description: the construction of a new road 66.50km long, 9m wide (7m cold asphalt its thickness is 5cm, two hot-mix asphalt shoulders 2m wide) + base course 20cm thickness (crushed aggregate 31.5mm) + Laterite sub-base 20cm + cutting and filling work + industrial works + Vertical and horizontal signalization.
Client: Ministère des Infrastructures - Direction Générale des Routes
Project Value: EUR 136 699 38
Starting Date: 2/7/2009
Expected Completion Date:  31/7/2011
Owner:  Ministry of Infrastructure and Transport - Directorate General of Roads
Financing Agency: 57.84% Chad Government
    16.84% Islamic Development Bank
    25.39% BADEA
Technical Details: 
Work Volume:  337 969 384 25 CFA francs (136 699 38   Euro)