Shendi-Almatma Bridge - Sudan

Bridges & Flyovers   ::  Completed Projects   ::  2010  ::  

Project Owner: Dams Implementation Unit
Consultant: Al Dar Engineering Consultancy
Contractor: Joint Venture of Arab Contractors Company (Sudan Branch) as the executing party and Petrohelp (RAM) as the Project Financier
Project Location: Shendi City, Nile River State, Northern Sudan
Starting Date: January 2, 2006
Completion Date: July 7, 2009
Initial Handing-Over Date: July 7, 2009
Final Handing-Over Date: September 6, 2010
Project Description:
Construction of a reinforced concrete bridge spanning the Nile River, with a total length of 660 meters and a width of 20.5 meters. The cross-section consists of 4 traffic lanes (2 lanes in each direction) in addition to pedestrian sidewalks. The scope of work included the execution of deep foundation, concrete piers, and the complete superstructure, providing a vital connection between the cities of Shendi and Al Matamma.