Kurimat II Combined Cycle Power Plant Project of 750 MW - Egypt
Power Stations
:: Completed Projects
:: 2008 ::
The plant is aimed to produce electrical power of 750 MW. It is based on the combined cycle technique that utilises both Steam and Gas for the turbine generators. The amount of reinforced concrete is 40,000m3, the weight of the steel structures are of 3000 tons, the amount of the excavated material is 300,000 m3 , and around 9,000 m length of 60cm diameter piles. Our scope also includes the construction of a duct bank for the pipe lines, the construction of 55 buildings, tanks, water purification unit as well as the pipes networks