Pharco International Pharmaceuticals Factory - Saudi Arabia
Industrial Plants
:: Ongoing Projects
:: Starting Date : 2024 ::
Client: Pharco International Pharmaceuticals Company
Client Consultant: Eng. Abdul Razzaq Hakim Office for Engineering Consulting
Project Duration: First phase - 30 months
Second Phase: 18 months
Total area of ??the factory: 62 thousand m²
Area of ??the first phase: 16 thousand m²
Area of ??the second phase: 9.5 thousand m²
Project Components:
· Production building
· Raw materials warehouse
· Manufactured materials warehouse
· Service Building A
· Service Building B
· Mosque
· Security chamber
· Electricity chamber
· Water tank for fires
· Water tank
· Fuel tank
· Fencing works