The Minister of High Education held a meeting to accelerate the execution of the university projects and the faculties which will be built.
AC Projects Manager in Damietta stated that the works divided into different phases with a total value EGP 400 million. The 1st phase was accomplished, it included that followings: 3 lecture halls each one has 30 grade stands which accommodate 250 students; besides 2 classrooms buildings includes 40 classrooms each one accommodates 150 students. 65% were accomplished from the 2nd phase which has the same scope of works as the 1st phase, 25% were implemented from the 3rd phase which includes the following: 2 lecture halls each one accommodate 850 students, in addition to resuming the works of the university's wall which is 3.1km length and total cost EGP 15 million… it will be accomplished soon.
Damietta Branch is carrying out the infrastructure with a total value EGP 215 million.